Skip Navigation

PJM Says $3 Billion Needed To Prepare Its Grid For Renewables Influx

May 24, 2022

by Peter Maloney
APPA News
May 24, 2022

As much as $3 billion will needed to be invested in grid enhancements to accommodate a growing amount in renewable resources expected in the PJM Interconnection region, according to a new report by the regional transmission organization.

The Grid of the Future: PJM’s Regional Planning Perspective report aims to ensure that PJM’s grid maintains the reliability and operational flexibility needed to address key drivers that are changing the face of the industry.

Over the next 15 years, PJM anticipates more than 100,000 megawatts (MW) of onshore wind, offshore wind, solar power and energy storage resources will come online in the PJM region, which already has 15,000 MW of renewable resources in service.

“The grid of the future is happening now, and this paper details the road map that will help us plan the transmission system to enable the shift to renewable generation resources that are smaller, more dispersed, and more variable in output than the existing fleet,” Suzanne Glatz, director of strategic initiatives and interregional planning at PJM, said in a statement.

The PJM region includes all or part of 13 states and the District of Columbia.

In the report, PJM planners identified and examined industry trends driving grid expansion, including generation development, evolving load characteristics, emerging transmission technologies and resilience.

The resulting road map for PJM’s Regional Transmission Expansion Plan (RTEP), which identifies transmission system additions and improvements needed to maintain the flow of electricity in the region, encompasses four focus areas.

PJM said it would conduct transmission build-out scenarios studies this year that will build on its renewable integration and offshore wind studies and include further analysis of the potential impacts of greater transportation and building electrification.

PJM said it would continue to conduct targeted reliability studies to explore generation and transmission attributes such as reactive control, stability, system inertia and frequency control, and short-circuit impacts.

PJM said it would also continue to study and implement improvements to its RTEP process. In April, PJM’s planning committee endorsed a proposal aimed at moving generation and other projects through its planning pipeline more quickly to help clear the current backlog.

And PJM said the road map also focuses on regulatory policy impacts that will inform new reliability criteria for such eventualities as extreme events, state electrification policies and Federal Energy Regulatory Commission (FERC) action on regional transmission planning.

In April, FERC directed grid operators to provide information regarding their changing system needs and plans for potential reforms.

Department of Energy Launches $3.5 Billion Carbon Capture And Storage Program

May 23, 2022

by Paul Ciampoli
APPA News Director
May 23, 2022

The U.S. Department of Energy (DOE) on May 19 released a notice of intent (NOI) to fund the infrastructure law’s $3.5 billion program for carbon dioxide (CO2) capture and storage.

The Regional Direct Air Capture Hubs program will support four large-scale, regional direct air capture hubs that each comprise a network of carbon dioxide removal (CDR) projects.

DOE noted that direct air capture is a process that separates CO2 from ambient air. The separated CO2 is then permanently stored deep underground or converted for use in long-life products like concrete that prevent its release back into the atmosphere.

Each of the projects selected for the Regional Direct Air Capture Hubs program will demonstrate the delivery and storage or end use of removed atmospheric carbon.

The hubs will have the capacity to capture and then permanently store at least one million metric tons of CO2 from the atmosphere annually, either from a single unit or from multiple interconnected units. 

For more information, read the NOI here.

DOE will host a virtual Carbon Negative Shot Summit on July 20 and 21, 2022.

Fitch Affirms Connecticut Municipal Electric Energy Cooperative, Transmission Entity Ratings

May 23, 2022

by Paul Ciampoli
APPA News Director
May 23, 2022

Fitch Ratings has affirmed ratings for Connecticut Municipal Electric Energy Cooperative (CMEEC) and Connecticut Transmission Municipal Electric Energy Cooperative at “AA-.” The rating agency cited, among other things, ample liquidity, very low leverage and a strong operating risk profile.

The Rating Outlook is Stable.

Fitch affirmed the following ratings at AA- for CMEEC:

It also affirmed the AA- rating for $16.3 million 2021 series A, transmission system revenue bonds for Connecticut Transmission Municipal Electric Energy Cooperative.

The Connecticut Transmission Municipal Electric Energy Cooperative was created by CMEEC in 2009. As a separate joint action agency, it acquired local transmission assets in order to provide transmission services required by CMEEC for its members and customers.

Fitch said that the ‘AA-‘ long-term bond ratings and IDR for CMEEC and the Connecticut Transmission Municipal Electric Energy Cooperative “reflect very strong revenue defensibility, a stable consolidated financial profile, with ample liquidity and very low leverage, and a strong operating risk profile.” The rating “also incorporates limited capital spending needs and a declining debt burden, which should allow leverage ratios to remain very low,” Fitch said.

Revenue defensibility is based on the long-term, all-requirements contracts and strong member credit quality that supports CMEEC’s revenue base, Fitch said.

“Operating costs are low, although energy supply is concentrated in near-to-medium term market power purchases, subjecting CMEEC to potential variability in market pricing. A comprehensive hedging policy helps mitigate this risk, although costs are still expected to rise. Capital plans are limited to minor maintenance with no new debt requirements projected through 2026,” it said.

“We are pleased by this rating affirmation,” said CMEEC Chief Executive Officer Dave Meisinger. “We believe Fitch recognized our strong overall financial profile and metrics, combined with appropriate long-term decisions such as the recent divestiture of our largest generation asset and a renewed focus on mapping out a path toward cost-effective reduction of our carbon footprint.”

Meisinger concluded that, “our stable ratings outlook helps ensure that CMEEC and its member municipal electric utilities will have competitive access to financial markets, which further positions the CMEEC members to maintain their reasonable retail electric rates.”

CMEEC’s member municipal electric utilities include Norwich Public Utilities, Jewett City Department of Public Utilities, Groton Utilities, Bozrah Light & Power, Third Taxing District of the City of Norwalk and South Norwalk Electric and Water.

President Biden Announces Intent To Renominate FERC Chairman Glick

May 21, 2022

by Paul Ciampoli
APPA News Director
May 21, 2022

President Biden on May 20 announced his intent to renominate Chairman Richard Glick as a member and Chairman of the Federal Energy Regulatory Commission (FERC). 

Glick, a Democrat, joined FERC as a commissioner in November 2017, having been appointed by President Trump.  He was elevated to Chairman by President Biden in January 2021. 

Glick’s current term expires June 30, 2022, although he could continue to serve through the end of the year. 

Glick’s renomination would require confirmation by the Senate.

Public Power Utilities Take Proactive Approach In Response To Supply Chain Challenges

May 21, 2022

by Paul Ciampoli
APPA News Director
May 21, 2022

Public power utilities are taking a proactive approach when it comes to meeting the ongoing challenges caused by supply chain disruptions through a series of actions that include working to boost inventory levels, placing orders into next year and expanding communication and relationships with developers.

[This is the second of a three-part series detailing public power’s response to supply challenges. Click here to read the first part of the series].

Lenoir City Utilities Board Sends Letter to Developers And Contractors

On March 15, 2022, M. Shannon Littleton, General Manager for Tennessee public power utility Lenoir City Utilities Board (LCUB), sent a letter to developers and contractors related to supply chain issues.

“Due to LCUB’s rapid growth and supply chain issues that the entire nation is facing, our procurement, engineering, and operations teams have become increasingly concerned about inventory of materials like transformers, power poles and meters,” Littleton wrote.

“As suppliers started to miss delivery dates, our teams began to meet regularly to develop a strategy to mitigate the impact of the delays through our design, procurement, and construction processes. We are managing inventory the best we can by creating alternative designs to maximize efficiency and seeking out new products and manufacturers,” Littleton said in the letter.

“Even with our efforts, more must be done to ensure we have adequate reserves to address weather events and provide permanent power to a growing system,” he said.

“We have decided to reserve single-phase equipment for completed construction projects and service restoration, when needed. Single-phase equipment is used primarily for residential and small commercial projects. The impact to builders is they will not be able to use a temporary power supply during construction unless there is existing infrastructure that we can connect to; they will have to rely on a generator,” Littleton wrote, adding that new permanent installations may also experience delays.

“There is no exact timeline on a resolution, but this situation is very fluid and will improve in time as equipment manufacturing delays are rectified,” he said in the letter.

Nebraska’s North Central Public Power District Keeps Eye On Supply Chain

In a recent Q&A with Public Power Current, Doyle Hazen, General Manager and CEO of Nebraska public power utility North Central Public Power District (NCPPD), described how NCPPD has taken a proactive approach when it comes to addressing supply chain issues.

“NCPPD has been monitoring the supply chain and the material markets through our relationships with our vendors,” he said. “We started ordering additional material and special equipment (transformers and reclosures) in late 2021. Proactively, we have been ordering into 2023 to stay ahead of our normal maintenance requirements, our work plan projects and expected growth of our system,” Hazen noted.

“The relationships we have with our vendors and other service providers are key in NCPPD’s ability to provide services and build projects on time. By knowing early where the market was going with our purchases both in price and availability, NCPPD was able to meet its customers’ needs. Although there is no guarantee of continued supply in any number of items, NCPPD monitors supply on a monthly, weekly and daily basis,” he said.

Mason PUD Issued Supply Chain Disruption Alert

Washington State’s Mason PUD 3 in September 2021 issued an alert in which it said that supply chain disruptions, unpredictable lead times, and unexpected price spikes of common materials “has the PUD and its customers increasingly uneasy about being able to meet construction timelines for electrical and fiber optic projects.”

The PUD said it was monitoring the situation very closely with its suppliers. “During this period, Mason PUD 3 is working to boost our inventory levels and search for additional product beyond our normal supply chains and construction practices. Although we don’t want to cause alarm, we do think that customers need to prepare accordingly,” it said.

The PUD said at the time it issued the alert that it was seeing major shortages and issues in the following areas related to the utility industry:

JEA Official Details Mitigation Strategies

At a February 2022 board meeting for Florida-based public power utility JEA, Jenny McCollum, JEA’s Chief Procurement Officer and Director of Procurement and Inventory Planning, said that “JEA started to see major disruptions around the beginning of 2021 and felt the impact across most of our inventory items.”

She said that “the specialized electric items were hit the hardest at first, followed by our water wastewater materials and then our safety items. More recently, though, we have felt impacts across all commodities including execution of our capital projects.”

McCollum said that “all of the areas of the supply chain are being affected,” which starts with the inability of manufacturers to source raw materials, transportation issues due to port closures, shipping container shortages, increased fuel costs and difficulty in hiring staff,” which has prevented most manufacturers from being able to meet normal demand, resulting in a reduction in capacity.”

She said that “the raw materials that are affecting us the most” are steel, copper, resin, aluminum and brass. The materials most impacted include transformers, valves and fittings, wire and cable, manholes and safety supplies.

“This crisis has caused focus, the need for speed and flexibility and collaboration across the company to take a comprehensive approach to mitigation efforts,” McCollum said.

Among other things, JEA is reducing terms to new contracts “and we’re adding flexibility to make price adjustments to align to the changing market.” In addition, JEA has diversified its supply base.

She pointed out that one key advantage for JEA is its use of a category management approach to procurement. This approach allows JEA “to be in a position to be nimble and quick and gives us a holistic view to all contracts and future spend plans.”

McCollum also said that “we’re expanding our communication and relationships with developers on their future plans. We are also partnering with suppliers to reserve capacity.”

At the same time, JEA is keeping an eye on the demand side of the equation when it comes to supply chain issues.

McCollum noted that the expansion of electric vehicles means that JEA is competing with EV manufacturers for the electric grade core steel “that we use in our transformers. So where their consumption in the past has been insignificant, we are seeing a major shift and there aren’t many suppliers in the market that can keep up with the growing demand.”

One new way that JEA is addressing current supply chain issues is by harvesting transformers. That means if there are transformers in JEA’s territory that are not being utilized for load due to businesses moving to another location in Jacksonville or going out of business, the utility pulls that transformer from the field and sends it to investment recovery to refurbish it. JEA then places it back into the system for new developments or repair/maintenance work.

Hannibal Board of Public Works General Manager Details Supply Chain Issues at Board Meeting

Darrin Gordon, General Manager of Missouri public power utility Hannibal Board of Public Works, addressed supply chain issues at a March 21, 2022, Hannibal Board of Public Works board meeting.

At the meeting, Gordon noted that APPA has reported that nationwide, the U.S. supply chain for electric grid equipment is becoming increasingly disrupted and that utilities were reporting increasing scarcity of electric grid components, with transformers and wires becoming scarcer.

“Those are essential,” Gordon said. “Every single one of our customers is touched by those items and with that, as that scarcity increases,” so does the delivery time and costs are escalating “and we haven’t seen the end of that yet.”

He noted that “consistently, we’ve always tried to maintain a stockyard of those parts that we may need.”

In the short run, the utility has been able to acquire items off the market, but “that market is getting more and more scarce and that stockpile that we have may become less and less adequate and the cost of keeping that is going to increase.”

TVPPA Communications Advisory Group Launches Supply Chain Toolkit

Meanwhile, the Tennessee Valley Public Power Association Inc.’s (TVPPA) Communications Advisory Group has developed a supply chain toolkit of resources.

TVPPA is the nonprofit, regional service organization that represents the interests of consumer-owned electric utilities operating within the Tennessee Valley Authority (TVA) service area.

TVPPA created the communications toolkit in response to member discussions about the challenges of sharing information about supply chain disruptions, particularly as they relate to transformers and other materials critical to servicing the needs of consumers and communities.

TVPPA members include both municipal and electric cooperatives, and they serve more than nine million people in Alabama, Georgia, Tennessee, Mississippi, Kentucky, North Carolina and Virginia.

Klickitat PUD Faces Critical Electric System Equipment Shortages

In late March 2022, Washington State’s Klickitat PUD said that it was starting to experience critical electric system equipment shortages due to the global shortage of materials and longer delivery delays from many vendors.

Jim Smith, the PUD’s General Manager, said that with material delivery delays and increased construction volumes, the utility was short on stock for its standard pad mounted transformers. These transformers take high voltage power from the PUD’s distribution lines and convert it to the 120 and 240 volts delivered to residences and businesses when underground power lines are used.  Transformers are on order and the PUD expects deliveries throughout the year, it said.

“We have been communicating with new customers and developers for months that we were expecting these shortages,” said Smith in a statement. “Existing customers should also realize that we are facing the same supply chain issues that they are seeing in stores. Delivery times are getting longer and prices are increasing across many materials.”

He noted, for example, that these transformers “normally have about a 16-week delivery time and were $1,500 each a year ago. Delivery is now more than a year out and they are being quoted at $6,000 each.”

Compounding the supply chain problem is a large increase in new construction in Klickitat County, the PUD said. The PUD would normally see about $1.4 million in new electric construction activity each year. In 2021, this increased to $2.8 million and the same is expected for 2022.

“The PUD Commissioners have directed staff to commit the funds required to allow us to keep two years of inventory in stock, rather than the normal six to twelve months,” said Smith. “We have the funds to be able to acquire these additional materials to support the increased growth in the county, but with limited supply and elevated usage, there is only so much we can do,” he said.

Department of Energy Extends Application Deadline For Civilian Nuclear Credit Program

May 21, 2022

by APPA News
May 21, 2022

The U.S. Department of Energy (DOE) on May 18 extended the deadline for applications and sealed bid submissions under the $6 billion Civil Nuclear Credit (CNC) Program that is aimed at supporting the continued operation of U.S. nuclear reactors.

Owners or operators of nuclear reactors most at risk of premature closure due to economic hardship have 47 more days from May 18 to submit applications for certification and sealed bids for credits. The deadline for the first CNC award cycle is now 11:59 p.m. Mountain Time on July 5, 2022.   

The first CNC award cycle is open to owners or operators of U.S. nuclear reactors that have already announced publicly their reactor is projected to close prior to September 30, 2026, due to economic factors. This ensures that the first award cycle is available to the reactors most at risk of imminent closure, DOE said. DOE published guidance on how to apply in April 2022. 

DOE is simultaneously developing guidance for the second award cycle under the CNC program, which will be open to more reactors. The next opportunity to apply will be in the first quarter of fiscal year 2023. 

Additional information is available here.

MEAG Power Names Reiko Kerr As New Senior Vice President and Chief Financial Officer

May 21, 2022

by Paul Ciampoli
APPA News Director
May 21, 2022

MEAG Power on May 20 announced that Reiko Kerr has been named senior vice president and chief financial officer, filling the vacancy resulting from Edward Easterlin’s recent retirement.

Kerr joins MEAG Power from the Los Angeles Department of Water and Power (LADWP), where she was senior assistant general manager. She will join MEAG Power effective July 18.

Kerr has 22 years of utility industry experience in public power, including 16 years at Riverside Public Utilities (RPU) in Riverside, Calif. She served as chief financial officer at RPU, among other executive positions in power supply and risk management, before joining LADWP in 2016.

Georgia-based MEAG Power is a nonprofit, statewide generation and transmission joint action agency. MEAG Power has over $9 billion in assets, delivered 10.6 million megawatt-hours of energy in 2014, and owns more than 1,300 miles of high-voltage transmission lines and nearly 200 substations.

NERC Summer Assessment Sees ‘Elevated’ Reliability Risks In The West, MISO

May 21, 2022

by Peter Maloney
APPA News
May 21, 2022

Parts of western North America face an “elevated or high risk” of energy shortfalls this summer because of predicted above-normal temperatures and drought conditions and electric reliability in the Midcontinent ISO (MISO) is at “high risk” because of capacity shortfalls, according to the 2022 Summer Reliability Assessment released by the North American Electric Reliability Corp. (NERC).

The expected continuation of western drought conditions poses several threats to electric reliability, NERC said. Below normal snowpack can result in lower-than-average output from hydro generation in a region that depends on energy transfers to balance electric supply and demand.

In particular, the California-Mexico (CA/MX) assessment area and the Southwest Reserve Sharing Group (SRSG), depend on “substantial electricity imports” to meet demand on hot summer evenings and at times when wind and solar resources are low.

Texas, the Southwest Power Pool (SPP), and Saskatchewan, in particular, are at elevated risk of energy emergencies during extreme conditions, the NERC report said, pointing out that in addition to putting a strain on electrical equipment, high temperatures also contribute to high demand.

The report also noted that continuing drought conditions over the Missouri River Basin could adversely affect SPP thermal generators that use the Missouri River for cooling.

Drought conditions can also exacerbate wildfires, NERC said, noting that government agencies are warning of the potential for above-normal wildfire risk across much of Canada, the U.S. South Central states, and Northern California. Wildfires can affect the reliability of transmission lines and the smoke from wildfires can cause diminished output from solar power resources, NERC said.

NERC also warned that the risk of unexpected tripping of solar photovoltaic resources during grid disturbances continues to be a reliability concern. In May and June of 2021, Texas experienced widespread solar loss events like those previously observed in California and four additional solar loss events occurred between June and August 2021 in California. During these events, widespread loss of solar resources was coupled with the loss of synchronous generation, unintended interactions with remedial action schemes, and some tripping of distributed energy resources, NERC said.

NERC also singled out the risks facing MISO, saying the region is at “high risk” because it faces capacity shortfalls in its north and central areas during both normal and extreme conditions because of generator retirements and increased demand.

Load serving entities in four of 11 MISO zones entered the annual planning resource auction (PRA) in April 2022 without enough owned or contracted capacity to cover their requirements, and peak demand projections have increased by 1.7 percent since last summer due in part to a return to normal demand patterns that were altered during the pandemic.

Even more impactful, NERC said, is the drop in capacity in the most recent PRA. MISO will have 3,200 megawatts (MW), representing 2.3 percent, less generation capacity than in the summer of 2021.

In addition, at the start of the summer, MISO will be without a transmission line connecting its northern and southern areas as restoration continues on a four-mile section of a 500-kilovolt (kV) transmission line that was damaged by a tornado in December 2021.

MISO system operators “are more likely to need operating mitigations, such as load modifying resources or non-firm imports, to meet reserve requirements under normal peak summer conditions,” NERC said. If there are extreme temperatures, higher generation outages, or low wind conditions MISO’s north and central areas will be exposed to “higher risk of temporary operator-initiated load shedding to maintain system reliability,” the NERC report said.

Supply chain issues and challenges commissioning new resources are also a concern in areas where those resources are needed for reliability during summer peak periods, NERC said. The report identified CA/MX and SRSG as areas that have “sizeable amounts of generation capacity in development and included in their resource projections for summer.”

In addition, coal-fired generators are having difficulty obtaining fuel and non-fuel consumables as supply chains are stressed, NERC said.

While no specific reliability impacts are foreseen, coal stockpiles at power plants are relatively low compared with historical levels, and some operators report challenges in arranging replenishment due to mine closures, rail shipping limitations, and increased coal exports, the report said.

Outside of MISO and the Western Interconnection, all other regions have sufficient resources to manage normal summer peak demand and are at low risk of energy shortfalls from more extreme demand or generation outage conditions, the report said.

The entire electric system, however, faces cyber security threats from Russia and other potential actors amid heightened geopolitical tensions in addition to ongoing cyber risks. “Russian attackers may be planning or attempting malicious cyber activity to gain access and disrupt the electric grid in North America in retaliation for support to Ukraine,” the NERC report said.

The Electricity Infrastructure Sharing and Analysis Center (E-ISAC) continues to exchange information on cyber threats with members and post communications and guidance from government partners.

E-ISAC members are “encouraged to check in regularly to receive updates and to actively share information regarding threats and other malicious activities with the E-ISAC to enable broader communication with other sector participants and government partners,” NERC said in its summer assessment.

Public Power Utilities Respond To Supply Challenges, Detail Mitigation Strategies

May 19, 2022

by Paul Ciampoli
APPA News Director
May 19, 2022

Public power utilities across the country continue to grapple with supply chain issues across a range of materials but they are proactively responding to this challenge through a wide range of mitigation strategies.

Those challenges and mitigation strategies were detailed recently at the American Public Power Association’s (APPA) Supply Chain & Management Summit, which was held on May 5-6, 2022.

 [This is the first of a two-part series detailing public power’s response to supply challenges].

At the summit on May 5, Edward Thomas, Jr., Manager, Materials Demand, at Florida’s Orlando Utilities Commission (OUC), noted that utilities “have a strong track record when it comes to recovery preparations for weather events and natural disasters.”

However, the health crisis caused by COVID-19 “created some unique challenges” that he said were foreign to the industry such as widespread quarantines, workforce and supply chain disruptions “that further complicated our traditional contingency plans,” he said.

With respect to raw material shortages, Thomas said that low inventories have caused cascading issues with material production with manufacturers. There is also a backlog of orders. “Suppliers have reported to us that it is the sheer amount of demand for materials compounded by the shortages in skilled labor.”

As for the primary materials impacted by the supply chain crunch, Thomas mentioned transformers and switchgear, wire and cable, water meter and meter boxes and lids. Chemicals are also be affected. He noted in his presentation that during the height of the pandemic, OUC experienced shortages of oxygen used in its water plants to ozonate the water for disinfection and removal of hydrogen sulfide.

While the current state of the supply chain has presented a host of challenges, it also offers opportunities, Thomas said.

The way things have been done before “and business as usual is not an option for us any longer,” he said.

Thomas said in his presentation that there is increasing pressure on utilities, suppliers and manufacturers to transform and evaluate and review the planning of capital projects as well as regular scheduled maintenance.

He also highlighted communicating with strategic supply chain stakeholders on volume for the next quarter when available, which includes materials, utility planning, suppliers, manufacturers and customers.  

In outlining supply chain mitigation strategies and potential solutions, Thomas highlighted OUC’s strategic partnerships with suppliers and manufacturers. The utility holds monthly scheduled meetings with operations, suppliers and manufacturers to discuss orders and any delays. OUC has also collaborated with suppliers “to hold material at their location based on annual monthly usage, while our project orders were being shipped direct.”

OUC is also working to educate and notify developers and builders within its service area. A letter was drafted with assistance of OUC marketing and communications updating customers about delays and adjusting materials allocated for their specific phased projects, Thomas said.

Another summit panelist, Hud Allworth, Manager, Materials Management and Warehouse, at Washington State’s Snohomish PUD, noted that supply chain issues created more noticeable impacts to a wider range of materials by mid-2021.

Many materials providers and manufacturers were still closed or had reduced production. Others had difficulty ramping production back up, saw supply shortages, experienced transportation pressures and faced labor shortages.

Suppliers began notifying the PUD that lead times were increasing, Allworth said. “In September 2021, we went to our Board of Commissioners and asked for an emergency declaration” to address the supply chain pressures.

In his presentation, he listed the following critical materials impacted by the supply chain crunch:

With respect to mitigation strategies, Allworth noted the following in his presentation:

“We expect continued supply chain disruption” and anticipate this will remain a top priority for the PUD into 2023, he said.

Jeffrey Stewart, Director for Louisiana public power utility Lafayette Utilities System (LUS), spoke at the summit on May 6.

He noted that since 2017, Louisiana has been hit by tropical storms and hurricanes and detailed existing mutual aid activities involving LUS. Currently, mutual aid only covers labor and equipment necessary for power restoration, Stewart said.

APPA helps to coordinate mutual aid events and offers resources to its members related to mutual aid.

Mutual aid efforts have “strengthened the relationship of APPA members over time,” Stewart said. “The last thing we all want to do is experience a hurricane, but it happens. It’s part of what we do. It’s part of how we operate and getting the assistance from up to 2,000 other members is a huge, huge benefit to being a part of APPA.”

With respect to supply chain issues, Stewart said that LUS is seeing increased prices and a shortage of material across a range of areas. He noted a shortage of supplies in things like transformers and fleet vehicles.

LUS is “trying to find creative ways to get our material.” The utility is looking at the option of leasing standard vehicles and trucks. “We’ve discussed the idea of setting aside material” for storms. But there are not “a whole lot of solutions because the supply isn’t there to implement some things.”

Mutual Aid for Materials  

Stewart touted the idea of creating mutual aid for materials, “just like we do for the labor and equipment, especially during hurricane season.”

This would involve one centralized location for finding available materials and utilize three tiers of materials.

As things stand today, if a utility needs a specific type of transformer at a certain voltage level, “it may be 25, 35, a hundred phone calls before I can find anything and that’s regardless of material supply shortages or anything like that,” he said. “I don’t know everybody’s operating voltage.”

Other Public Power Utilities Also Addressing Supply Chain Challenges

Other public power utilities have also been grappling with supply chain issues.

In September 2021, Texas public power utility CPS Energy issued a news release noting that the coronavirus pandemic, labor shortages, and other events have caused major production interruptions for many manufacturers at an international scale.

“Current demand for products and supplies are dramatically exceeding the available supply, which is putting a strain on supplies that CPS Energy and other utilities use daily,” the utility said at the time.

CPS Energy said that an increasing list of raw materials were causing challenges for manufacturing including:

“CPS Energy is working diligently to minimize the impact of material supply shortages,” it said, noting that CPS Energy was taking a highly creative approach to the materials shortage challenges.

“These supply constraints are not unique to our community,” said Maria Garcia, CPS Energy’s Vice President of Supply Chain, in the news release. “Our peer utilities across the country are taking similar actions to ours such as diversifying their specifications and suppliers to allow for greater flexibility in procuring these critical items, without sacrificing product safety, resiliency and reliability.”

In a May 10 email update, CPS Energy spokesperson Dana Sotoodeh said it is important to note that when discussing supply chain challenges that San Antonio is one of the fastest growing metros in the nation.

She detailed the following general updates: 

CPS Energy has responded by diversifying its supplier base, expediting shipments where possible, negotiating contracts to keep current pricing in place and refurbishing equipment to increase its lifespan.

The utility is also:

New Braunfels Utilities

Another Texas public power utility, New Braunfels Utilities (NBU), posted a supply chain alert on its website in which it noted that developers of new construction are impacted due to material shortages for distribution wire, cable, and transformers to complete planned developments. “Lead time for these materials is now calculated in months rather than days. Buyers at NBU are working diligently to source these materials and find alternate sourcing when available,” the utility said in the alert.

NBU said that it had been notified by multiple vendors that its contracted deliveries of wire, transformers, and other equipment were significantly delayed due to dock delays, labor shortages, and other issues. In some instances, they are citing delays of up to 100 weeks, the utility noted.

“These delays of needed material and equipment will affect the start date for new construction projects,” NBU said.

It pointed out that it “is working diligently to locate alternative sources for the equipment needed to proceed with new construction projects. Our purchasing team is dedicated to finding additional vendors and materials to keep project delays to a minimum.”

To help mitigate the impact of supply chain issues, “any and all developer requirements must be completed prior to material and equipment being reserved. This means all easements, fees, and civil work are required to be completed before NBU will release a project to Purchasing to confirm the needed materials are available.”

Public Power Weighs In On Hydropower Licensing Issues At House Hearing

May 19, 2022

by Paul Ciampoli
APPA News Director
May 19, 2022

Rich Wallen, General Manager and CEO of Washington State’s Grant County PUD, recently warned of the negative consequences that could result from the removal of the Lower Snake River Dams in testimony he gave at a House hearing that examined proposed hydropower licensing changes.

Meanwhile, the American Public Power Association (APPA) said in a statement for the record for the hearing that the process for licensing non-federal hydro projects must be streamlined and reformed.

The hearing was held on May 12 by the House Energy and Commerce Committee’s Subcommittee on Energy.

Along with Wallen, other hearing participants were Malcolm Woolf, President & CEO, National Hydropower Association, Tom Kiernan, CEO, American Rivers, Mary Pavel, Partner, Sonosky, Chambers, Sachse, Endreson & Perry LLC, and Chris Wood, President & CEO, Trout Unlimited.

The primary focus of the hearing was to examine hydropower licensing and proposed changes recently put forth by groups involved in the “Uncommon Dialogue” effort, a forum created by the Stanford Woods Institute to bring together stakeholders to develop consensus policy, technology, and investment recommendations related to hydropower, river health, and dam safety.

Grant County PUD owns and operates two Columbia River dams and two smaller hydro generators that have a combined generating capacity of more than 2,100 megawatts. Priest Rapids and Wanapum dams, collectively known as the Priest Rapids Project, are licensed by the Federal Energy Regulatory Commission (FERC).

In his testimony, Wallen noted that the PUD supports H.R. 1588, the Hydropower Clean Energy Future Act, sponsored by Rep. Cathy McMorris Rogers, R-Wash.

The recently completed Columbia River System Operation Environmental Impact Statement studied the environmental, biological, power supply and socioeconomic impacts of the entire Federal Columbia Rivers System Operations. 

While one of the proposed alternatives was breeching the Lower Snake River Dams, the conclusion of the study was that the dams play a vital role in the Northwest power system and that their continued operation does not inhibit the existence of endangered or threatened salmon species.

“While we recognize some of the removal efforts contemplated under the Uncommon Dialogue are for non-powered dams, the predominance of dam removal in the dialogue at all is concerning,” Wallen told lawmakers at the hearing.

He pointed out that the Lower Snake River Dams were built to facilitate fish passage and actually achieve spring juvenile survival rates at 96% and summer migrating fish survival at 93%, meeting or exceeding performance standards. 

“Nonetheless, some stakeholders push for removal of the Lower Snake River Dams even though the fish in the neighboring undammed rivers are experiencing similar stresses and the fact that only three of the listed species even migrate up the Snake,” Wallen said.

The four Lower Snake River Dams are a critically vital component of the Bonneville Power Administration’s (BPA) low cost, carbon-free power supply, he went on to say.

“To remove the dams would result in massive rate increases to regional supply costs, increases in carbon emissions and increased risk of blackouts,” he said. “Replacement carbon-free resources are not available and cannot be easily or cheaply secured and require overbuild to counteract their intermittency.”

Under this future, the Lower Snake River Dams “will grow in importance, because they can act as giant, clean energy batteries, helping fill in these gaps for wind and solar.”

Wallen said that hydropower “provides dependable and carbon-free generation, when we need it and how we need it.”

While Grant PUD owns and operates its own hydropower dams, “we are concerned about the impact losing the Lower Snake would have for the entire region.”

He noted that the Western Electric Coordinating Council in its 2021 Western Assessment of Resource Adequacy issued a warning that every region comprising the Western grid is facing an abnormal risk of blackouts.

“We are also concerned about the price impacts, as the BPA has forecasted wholesale price impacts of 50% if the dams are removed and replaced with wind or solar plus batteries,” Wallen said. “This price hike could impact Grant PUD customers,” he said, noting that the PUD has priority rights to BPA-provided generation.

“In a carbon-constrained world, hydropower is increasingly vital for its emissions-free generation, load-following capabilities, grid stability and integrating intermittent resources that keep the lights on,” Wallen said.

APPA Statement For the Record

In its Statement for the Record, APPA noted that there is a significant potential for new hydropower to be generated at non-powered dams throughout the country and to increase output at existing hydropower facilities. “But there are excessive barriers to tapping this potential,” it said.

The Federal Energy Regulatory Commission (FERC) is the primary federal agency responsible for the licensing and relicensing of such non-federal hydroelectric projects, “but the process can be lengthy, difficult, costly, and uncertain for applicants,” APPA said.

It noted that under the Federal Power Act (FPA), FERC must establish requirements in conjunction with the license that give “equal consideration” to not only power needs, but also Endangered Species Act requirements, water quality issues, marine navigation, and other public-interest concerns. FERC must carefully evaluate many aspects of a hydropower project, but at the same time, state and federal agencies can impose “mandatory conditions” that FERC cannot balance or modify in the public interest.

“While it is appropriate to consider a broad array of factors, this process must be streamlined and reformed. Critical new additions to existing hydropower facilities are languishing under bureaucratic and often contradictory processes that can span a decade or more or which simply become too costly,” APPA said. “The byzantine licensing and permitting processes are also a significant impediment to simply maintaining existing hydropower capacity.”

Between now and 2030, 281 facilities representing nearly 14 gigawatts of hydropower generation and pumped storage capacity — roughly 30 percent of FERC hydropower licenses — are up for relicensing.

“We simply cannot afford to lose existing hydropower capacity without threatening to miss emission reduction goals and grid resiliency. Congress must streamline the licensing process by establishing FERC as the lead agency, giving it the authority to set and enforce schedules for the issuance of all resource agency authorizations and studies, and ensure any “mandatory conditions” are directly relevant to the project,” APPA argued.

Federal Tax Incentives

APPA said that another significant obstacle to the growth and retention of non-federal hydropower capacity is insufficient federal tax incentives on par with those available to other clean energy resources.

APPA noted that it strongly supports legislation introduced by Senators Maria Cantwell (D-WA) and Lisa Murkowski (R-AK), the Maintaining and Enhancing Hydroelectric and River Restoration Act of 2021 (S. 2306), that seeks to address this issue.

The bill would create a 30 percent tax credit to support upgrades at existing hydroelectric dams for qualified dam safety, environmental, and grid resilience improvements. “Critically, this credit would be available as a direct payment to public power utilities,” APPA said.

This provision is also included in a bill introduced by Representative Annie Kuster (D-NH), H.R. 4375, the Twenty-First Century Dams Act.

“It is critical that this provision be included in any energy tax credit legislation that may be considered this Congress,” the public power trade group said.

“Uncommon Dialogue” Effort

While APPA was not directly involved with the “Uncommon Dialogue” effort lead by the National Hydropower Association and a number of environmental and tribal organizations, it noted that many of APPA’s members are also members of the National Hydropower Association and were engaged as the proposal developed.

While APPA continues to believe that the hydropower licensing process requires more comprehensive reform along the lines of what was included in H.R. 3043 in 2017, “we appreciate the incremental changes included in the group’s recently (April 2022) released licensing reform proposals. We are particularly supportive of the proposed requirement that mandatory conditions under section 4(e) of the FPA be reasonably related to project effects on federal lands.” 

 With respect to other proposals put forth in by the Uncommon Dialogue group and associated legislation regarding dam removal, APPA said it opposes efforts to remove productive dams that provide, or have the potential to provide, clean and economic hydropower generation.

“Furthermore, proposals to appropriate funding for the Corps, Reclamation, and any other federal agencies for ‘dam related activities’ must include statutory text specifying that this funding cannot be incorporated into the rates paid by federal hydropower customers,” it said.

Federal Hydropower

APPA also said that federal hydropower and the Power Marketing Administrations are critical, though often overlooked, elements of the nation’s power supply.

APPA supports the continued existence and federal ownership of the PMAs and the sale of federally generated hydropower at cost-based rates and “strongly opposes any efforts to disproportionately assign costs to federal hydropower users for which they receive no additional benefits.”

National Hydropower Association

In his testimony at the hearing, the National Hydropower Association’s Woolf said that new and existing hydropower “is at risk due in part to the byzantine licensing and relicensing system.”

He said that the country is at the crest of a wave of hydropower licensing. “At the same time, relicensing takes 7.6 years to complete on average and often takes much longer than a decade.”

A recent industry survey found than more than 40 percent of hydropower industry asset owners said that they were actively considering decommissioning a facility, Woolf noted. “Alarmingly, 58 percent of facilities have submitted license surrender applications to FERC since 2010 including 17 in just the last two years.”

Reform of the hydro licensing process is urgently needed, he said, noting that the National Hydropower Association supports the joint license reform package.

A summary of the proposed changes, as well as the proposed changes to the text of the Federal Power Act (FPA) itself, are available here.